- Can conveyor assembly.
- Final positioning of the filler.
- Assembly and connection of the rinser with filtered air.
- Installation of can inspectors and control device.
- Can coder assembly before the empty can inspector.
- Introduction, positioning and anchoring of the capping machine, leveling and connection with the cap feeder.
- Positioning, leveling and assembly of lid conveyors.
- Installation of can turners in the section prior to level inspection.
- Introduction, positioning and leveling of pumps and intermix, connected to the filler.
- Installation of pipes for lubrication and cleaning of the foam of the filling machine.
- Electrical assembly of the can filling area and conveyors.